Weekly Update for West Grand Avenue Project

The contractor is continuing to pour sidewalk between 2nd Avenue and 4th Avenue as well as pavement in the intersection at 2nd Avenue.

For the week beginning Oct. 3, the remaining sidewalk work will be completed along with pavement patching at intersections of First, Second and Fourth Avenues as well as pavement marking. The entire project, with the exception of the sidewalk by the old Johnson and Hills building, should be complete by the end of the week if the weather cooperates.